MASTER SCHEDULING
INTRODUCTION
-The master production schedule (MPS)
-Is a plan for the production of individual end items
-It must be achievable and reflect a balance a balance
between required and available capacity.
DEVELOPING A
MASTER PRODUCTION SCHEDULE
-To maintain the desired level of customer service by
maintaining finish good inventory levels or by scheduling to meet customer
delivery requirements.
-To make the best use of material, labor and equipment.
-To maintain inventory investment at the required levels.
PRELIMINARY MASTER
PRODUCTION SCHEDULE
-To show the process of developing an MPS , an example, is
used that assumes the product is made to stock, an inventory kept, and the
product is made in lots.
MASTER SCHEDULE
DECISIONS
-The MPS should represent as efficiently as possible what
manufacturing will make.
-In each of the manufacturing environment make to stock,
make to order, and assemble to order master scheduling should take place where
the smallest number of product options exists.
MAKE TO STOCK
PRODUCTS
-A limited number of standard items are assemble from many
components.
-The MPS is usually a schedule of the actual customer
orders.
ASSEMBLE TO ORDER
PRODUCT
-Many end items can be made from combinations of basic
components and subassemblies.
FINAL ASSEMBLY
SCHEDULE (FAS)
-Assembly to customer order, I generally planned using a
final assembly schedule.
-Master production scheduling is done at the component
level.
-The FAS schedules customer order as they are received and
is based on the components planned in the MPS.
ENGINEER TO ORDER
-This is a form of make to order (MTO) product.
-The product is designed before manufacturing based on the
customer’s very special need.
-A bridge is an example
THE MPS AND
DELIVERY PROMISES
-Customer orders are satisfied from inventory.
-In either case, sales and distribution need to know what is
available to satisfy customer demand.
-As order are received, they ‘’consume’’ the available
inventory or capacity.
-Any part of the plan that is not consumed by actual
customer orders is available to promise to customer.
-Using the MPS, sales and distribution can determine the available to promise (ATP).
-This ATP allows delivery promises to be made and customer
orders and deliveries to be scheduled accurately.
-The ATP is calculated by adding scheduled receipts to the
beginning inventory and then subtracting actual orders scheduled before the
next scheduled receipt.
FORMULA ATP
ATP for period 1= On Hand – Customer orders due before next
MPS
=100-80
=20 Units
ATP for period 2= MPS scheduled receipts - Customer orders
due before next MPS
=100 – (10+10) =80 Units
ATP for period 4 =100-30 =70 Units
PROJECTED
AVAILABLE BALANCE
-Our calculation so far have based the projected available
balance on the forecast demand.
-Customer orders will sometime be greater than forecast and
sometimes less.
-Projected available balance is now calculated based on
whichever is the greater.
-For periods before the demand time fence it is calculated
as:
PAB =prior period PAB or on-hand balance +MPS-customer
orders
-For periods after the demand time fence, forecast will
influence the PAB so it is calculated usig the greater of the forecast or
customer orders. Thus the PAB becomes:
PB =prior period PAB+MPS- greater of customer orders or
forecast.
EXAMPLE:
Given the following data, calculated the projected available
balance. The demand time fence is the end of week, the order quantity is 100,40
are available at the beginning of the period.
No comments:
Post a Comment